Advanced agitator design shaves 60% off plant energy bill
07/04/2011 (Read full story here or download PDF)    Email to a friend   Comment on this article
Process engineers at AkzoNobel's Birmingham coatings plant are reporting energy consumption cut by more than 60%, with batch times reduced by 20 minutes, since installing EKATO agitators.

Advanced agitator design shaves 60 off plant energy billAkzoNobel's engineering manager Scott Love says the equipment was chosen to achieve those goals and also to reduce maintenance – together delivering a 300% improvement in plant throughput.

Love says that the plant manufactures water-based coatings and that growing demand meant fast action – particularly to solve ingrained process maintenance issues.
"We had a higher level of maintenance, due to a build up of material around the agitator shaft and heating coils, reducing heat transfer capability, which ultimately increases the process times and requires cleaning every three months," he explains.

A range of solutions, such as adding additional baffles and retrofitting impellers, had been tried, but none had offered the improvements needed.

AkzoNobel approached EKATO, and subsequently upgraded the existing reactor with that firm's Viscoprop impeller and electric motor technology, which saves energy by using a smaller 15kW motor.

"This smaller motor still achieves better mixing performance than the previous 75kW unit, with a lower capital investment," comments EKATO UK's technical sales engineer William Pocock.

With the installation complete, AkzoNobel's Birmingham plant confirmed a 20 minute reduction on its previously nine-hour batch times – due to improved heat transfer, better product circulation and reduced solids build-up on the internal heating coils – which also reduces the need for a chiller, resulting in further energy savings.

Love says that internal cleaning of the reactor has now become an annual procedure, as opposed to quarterly or between manufactured batches, so resulting in less down time and waste.

"This investment will significantly help our organisation to make strides with process reliability, energy consumption and environmental matters," conclude Greg Methven, AkzoNobel site manager at Birmingham. "This is a step toward achieving our sustainability ambitions for 2015, and beyond."
Payback on the investment will be under three years, he says.

 
Author
Brian Tinham
 
 
Download Articles
 
e2e.pdf
 
 
This material is protected by SOE copyright 2012.
See Terms and Conditions.
One-off usage is permitted but bulk copying is not.
For multiple copies contact the sales team.
 
Bookmark this article using:
 
Del.icio.us digg reddit Facebook StumbleUpon
 
 
Related Companies
Ekato Fluid
 
 
Related News
Baroness lifts the lid on new manufacturing plant
 
Engineering professor predicts 2 million more engineers from green growth
 
Weg gets ISO 50.001 for electric motor manufacture
 
Progressive future for UK manufacturing, says new report
 
St Richard’s hospital laundry saves £14,000 energy on new steam traps
 
 
Related Technology
Maintec 2012
 
Power play
 
Compressing costs
 
Energy efficiency is effective now
 
Energy event 2011
 
 
Related Products
ABB launches BlackBerry app energy calculator
 
ABB offers six-step energy saving plan for industrial plants
 
Compressed air savings revealed on new website
 
Rapeseed oil fuels green energy revolution
 
Lighting cuts carbon
 
 
Downloads
e2e.pdf