plant-engineer
Home Advertise Magazine Events Contact Us Login
Search     


River Ribble clean-up uses deep diaphragm wall shafts
24/08/2010 Email to a friend   Comment on this article
Geotechnical contractor Bachy Soletanche is using a storm water shaft, with deep diaphragm walls and cased secant piling, on a project for United Utilities.

River Ribble clean up uses deep diaphragm wall shaftsThe project, which started in May, with main contractor KMI Water (a joint venture between Kier Construction, J Murphy and Sons and Interserve Project Services), is to treat water bound for the River Ribble. It is due to run until October, and is worth £70m in total.

A 27m diameter shaft, adjoining a 22m deep 50x20m screening chamber and a 17m diameter shaft, constructed by Diaphragm Walling, will connect with nine additional cased CFA shafts.

These are on the north side, with links via a 3.5km tunnel constructed 30m below the ground by KMI Water, and, according to the companies, will pave the way for a cleaner river.

One of the south diaphragm wall shafts has been formed by 14 interlocking panels 1m thick by 20m deep. Between each panel, a CWS waterbar is being installed to stop water leaking through the joint, and to ensure maximum water tightness between adjoining panels.

Panels are being dug under a bentonite suspension, with reinforcement cages placed and concrete added into the trench.

Steve Mallinson, contract manager for Bachy Soletanche, explains that the Cased CFA, CSP technique forms a closed structure to act as a barrier in water-bearing soils and is ideal for a city centre project, such as the Preston Shafts.

He cites benefits as including: better tolerance than an uncased CFA secant wall; better appearance with reduced over-break; speedier operation than traditional kelly/casing rotary bored piling; reduced risk of flighting in poor soils; and a reduced risk of distress to adjacent structures.

"The large south side shafts are more than 20m deep, hence the use of the diaphragm walls which involve less construction joints than bored pile walls," says Mallinson.

"On the north side verticality has also been key throughout this project due to the nature of the interlocking between the male and female piles to ensure a watertight solution is created."
 
Author
Brian Tinham
 
 
This material is protected by SOE copyright 2012.
See Terms and Conditions.
One-off usage is permitted but bulk copying is not.
For multiple copies contact the sales team.
 
Bookmark this article using:
 
Del.icio.us digg reddit Facebook StumbleUpon
 
 
Related Companies
Bachy Soletanche Ltd
 
 
Related News
Welsh Water improves efficiency with new gearboxes
 
Pulsonic selects Watson-Marlow for wastewater samplers
 
Pulsar ultrasonics are no slouch to sludge
 
HRS Heat Exchangers gets eur 1 million EC R&D grant
 
Deritend takes Anglian Water multi-million improvement contract
 
 
Related Technology
Pulsar ultrasonics are no slouch to sludge
 
Wastewater treatment plant slashes down-time and maintenance
 
Wired for water
 
Going with the flow
 
Choppers cut Severn Trent costs
 
 
Related Products
WIMES high efficiency motors exceed IE2 and 3